Our participation has led to the successful implementation of dozens of large-scale projects. In order to clarify the main trends and opportunities of OTK Group companies’ we are giving examples of projects for which our participation allowed our customers to make a considerable economic advan
Services
Projects
Spare parts for industrial equipment
Clients
Actual topics
OTK-Association
Consultation

 




Rambler's Top100
Home / 

Projects

Our participation has led to the successful implementation of dozens of large-scale projects. In order to clarify the main trends and opportunities of OTK Group companies’ we are giving examples of projects for which our participation allowed our customers to make a considerable economic advantage.


Lumber sorter line
JSC "Novoyeniseiskiy Wood-Chemical Complex", Lesosibirsk
Project period: February – August 2016
Completed works: Foreign trade contract analysis, classification decision, opening of bonded warehouse, arrangement of receiving of permissive documents, preparation and control of shipping documents, services related to customs clearance
»»»
 

The production line for panels of wood chips (OSB)
JSC "Modern technologies of wood processing", St. Petersburg
Project period: April 2014 - Present
Works in progress: Classification decision of Federal customs service, Amendment of the classification decision, preparation of documents for exemption of the whole set of equipment from VAT, arrangement of delivery to Russia, full complex of services on customs clearance in Russia
»»»
 

Technological line for the production of silicon lenses by dry etching
LLC "Mapper", Moscow
Project period: May 2013 - Present
Ongoing work: Classification decision of Federal customs service; legal support of the project; arrangement of delivery to Russia, including transportation, insurance, consolidation and storage hardware components in EU; cooperation with suppliers; full range of services for customs clearance in Russia, supply of spare parts
»»»
 

Sawmill line
JSC "Lesplitinvest", Leningrad region, Priozersk
Project period: November - December 2014
Completed works: Classification decision of Federal customs service, consulting services on purchase contracts conclusion
»»»
 

Processing plant oilseed meal
LLC "Bio technology", Gorno-Altaisk
Project period: April - December 2014
Completed works: Classification decision of Federal customs service, preparation of documents for exemption of the whole set of equipment from VAT and customs clearance services in Russia
»»»
 

The line for the production of particle board (chipboard) line laminating chipboard panels
LLC "TOMLESDREV", Tomsk
Project period: June 2013 - July 2014
Completed works: Classification decision of Federal customs service, preparation of documents for exemption of equipment from VAT, advisory services on registration of foreign trade contracts and the use of customs classification decisions
»»»
 

Complex mixing equipment for a cable plant
JSC "Sibkabel", Tomsk
Project period: March - May 2014
Completed works: Classification decision of Federal customs service consulting services on purchase contracts conclusion
»»»
 

Hot-dip galvanizing line
CJSC "Nevsky steel mill"
Project period: August 2012 - May 2013
Completed works: Russian customs classification decision, preparation of documents for VAT exemption of the whole complex of equipment
»»»
 

Timber sorting line
JSC "Angara wood processing complex", Krasnoyarsk Territory
Project period: April 2013
Completed works: Russian customs classification decision, consulting services on purchase contracts conclusion
»»»
 

MRAM production plant on silicon wafers Ø300 mm
«Crocus Nano Electronics» Ltd. Co., Moscow
Project period: April, 2012 till present time.
Work in progress: Classification decision of Federal customs service, preparation of documents for exemption of MRAM production plant from VAT, consulting services on purchase contracts conclusion, consolidation and storage of equipment components in EU, arrangement of delivery to Russia, full complex of services on customs clearance in Russia.
»»»
 

Sawmill line
LLC "Norwood SM" Syktyvkar
Project period: November 2011 - February 2012
Completed works: Classification decision of Federal customs service, consulting services on purchase contracts conclusion, preparation of shipping documents, the opening of the consignee customs warehouse, full complex of services on customs clearance in Russia.
»»»
 

Plant for production of Li-Ion batteries
«LIOTECH» Ltd. Co., Novosibirsk
Project period: February, 2011 - April, 2011
Completed work: Classification decision of Federal customs service, consulting services on foreign trade contract, shipping documents
»»»
 

Molecular Beam Epitaxy System
«Connector Optics» Ltd. Co., St-Petersburg
Project period: December, 2010 - February, 2011
Completed work: Full range of services on customs clearance, consulting services on foreign trade contract, shipping documents.
»»»
 

Plant for manufacture GRP pipes and coupling
ZAO «Stekloplastic», Stavropolsky region
Project period: January 2010 - August 2010
Manufacture of glass fibre reinforced polyester (GRP) pipes by continuous winding of Autonational is the latest technology. Equipment is for the production of pipes and couplings in range from DN300 to DN3000.
»»»
 

Plant for manufacture of washing machines
ООО «Electrolux Rus», Saint-Petersburg
Project period: May 2010
The international company Electrolux decided to transfer plant for manufacture of washing machines to another state. On contract conditions it was necessary to disassemble all equipment of factory, to prepare the documentation and to order transport within 2 weeks.
»»»
 

Pellets manufacturing plant
ОАО «Vyborgskaja Celluloze», Leningrad region
Project period: February 2010 - May 2010
The pellets manufacturing plant by capacity 1 million t/year is the largest pellets plant in Europe and the world for today.
»»»
 

Plant for MDF manufacture
ZАО «Timber processing complex «Partner-Tomsk», Тomsky region
Project period: March 2009 – November 2009
Production capacity of the plant - 800 м3 MDF per day (264 000 м3 MDF per year). Currently, the project has no analogues in CIS countries.
»»»
 

Retrofit installation of pulp and paper mill
OAO " Mondi Syktyvkar ", Syktyvkar, Republic of Komi
Project period: February, 2008 till the present time.
Completed work: 8 classification decisions of Federal customs service, consulting services, control of shipping documents, full range of services on customs clearance.
»»»
 

Saw mill
OAO " Boguchan timber-processing complex ", Boguchany village, Krasnoyarsk region
Project period: April, 2008 till the present time.
Completed work: 4 classification decisions of Federal customs service, control of shipping documents, full range of services on customs clearance, arrangement of delivery.
»»»
 

Plant for MDF manufacture
OAO " Rimbunan Hijau MDF ", Khabarovsk
Project period: March, 2008 – July, 2008.
Completed work: Classification decision of Federal customs service, consulting services on foreign trade contract, shipping documents and customs clearance.
»»»
 

Plant for manufacture of wood particle boards
OAO " Gagarin plywood manufacturing plant", Smolensk region
Project period: August, 2007 –June, 2008.
Completed work: 3 classification decisions of Federal customs service, consulting services on foreign trade contract, delivery and customs clearance.
»»»
 

Plant for production of FRHC copper rod
OAO " Kamenskaya Katanka ", Kamensk-Uralsky, Sverdlovsk region
Project period: October, 2007 – March, 2008.
Completed work: Classification decision of Federal customs service, consulting services on foreign trade contract, delivery and customs clearance.
»»»
 

Plant for production of neutral sulfite semichemical
OAO " Ilim group ", St-Petersburg
Project period: August, 2007 –January, 2008.
Completed work: Classification decision of Federal customs service, consulting services on foreign trade contract, shipping documents and customs clearance.
»»»
 

Aluminum alloy slab thermo mechanical treatment plant
Chkalovski (Limited liability company), Sverdlov district,Kamensk-Uralsky City
Progect period: June, 2007 – January, 2008.
Completed work: equipment importation, 5 resolutions of the State Customs Committee of the Russian Federation, certification, opening of a temporary customs supervision zone.
»»»
 

Factory of drawing an external anticorrosive covering on pipes of the big diameter
PJSC “VSW” (Public Joint- Stock company “Vyksa Steel Works”), Vyksa, Nizhny Novgorod region                                                                              Project period: March, 2007 – January, 2008.                                                       Completed work: resolution of the State Customs Committee of the Russian Federation, the control of transport documents, preparation of documents for customs processing.
»»»
 

Industrial gas oven installation for homogenization.Line for cutting of aluminum plates
OAO " Alkoa Metallurgist Rus ", the Rostov area, White Kalitva
Project period: June, 2007 – December, 2007 April, 2008 till the present time. Completed work: resolution of the State Customs Committee of the Russian Federation, the control of transport documents, preparation of documents for customs processing.
»»»
 

Gantry crane with lifting capacity 18,5 x 2 tons
ZAO " Izhorsky pipe mill ", St-Petersburg
Project period: July 2007 – December, 2007.
Completed work: Full range of customs services.
»»»
 

Big diameter pipes production plant
Izhora Pipe Plant (Joint-stock company), Saint-Petersburg City
Project period: June, 2005 – October, 2006
Completed work: 3 resolutions of the State Customs Committee of the Russian Federation, a full range of services as to customs processing, correction of delivery schedule.
»»»
 

Black liquor evaporation equipment; transport and packing line for moving and packing rolls
Kotlas Pulp and Paper Plant, Koryazhma City, Archangelsk Region
Project period: April, 2005 – October, 2006
Completed work: resolution of the State Customs Committee of the Russian Federation in respect to the importation of black lye evaporation equipment as well as of transport and packing line for the purpose of moving and packing rolls as to the uniform code of foreign economic activity commodity nomenclature without classification resolution, a full range of services as to customs processing
»»»
 

Sunflower-seed oil production plant
"Sanoil-Bakar" (Limited liability company), Krasnodare Territory
Project period: September, 2004 – May, 2006
Completed work: a full range of services in regard to customs processing, delivery and organization, 3 resolutions of the State Customs Committee of the Russian Federation, importation of equipment, as part of a setting up costs.
»»»
 

Washer component production plant
Euromolding (Limited liability company), Saint-Petersburg City
Project period: February – November of 2005
Completed work: a full range of services in respect to customs processing, importation of equipment as part of the start up expenses according to the code for foreign economic activity commodity without classification resolution.
»»»
 

Dry building mix production plant
Dry mix production plant, Moscow City
Project period: May – July of 2005.
Completed work: a full range of services. The equipment was imported for the company’s establishment.
»»»
 

Woodworking complex
First woodworking plant (Limited liability company), Kirishi City, Leningrad Region
Project period: January – July of 2004
Completed work: Full range of services on customs clearance of equipment as the investment to the authorized capital.
»»»
 

Plastic film metallization equipment
Plastic film metallization equipment, the city of Saint-Petersburg
Project period: September – November of 2003
Completed work: Full range of services on customs clearance of equipment as the investment to the authorized capital.
»»»
 

Refinery plant
Astrakhan
Project realization term: August, 2003.
Completed work: delivery organization, customs processing.
The freight included oversized parts – e.g. refinery column with the length equal to 29 meters and diameter equal to 4 meters.
»»»
 

Modular concentrating mill
Modular concentrating mill, Magnitogorsk City
Project realization term: 2002
Completed work: Delivery and customs clearance.
»»»
 

Bituminous-polymeric material production plant
Bituminous-polymeric material production plant, the city of Moscow
Project period: January-December of 2002
Completed work: Full range of services on customs clearance, classification decision of State Customs Committee.
»»»
 